All projects have risks. These could include
resource shortages, late changing requirements, budget shortfalls, overly high
problem report rates, etc. Good project management requires managing
against risks. Each risk should be identified. The top risks should
receive regular attention.
Prioritize Risk
Risks should be prioritized. They should each
have an owner empowered to resolve the issue.
Specific risks are far more detailed than those just
listed. See the following Top Risks List for examples of problems
and how they might be monitored and addressed. Clearly, each organization
will need to tailor this approach to best fit its needs.
Top Risks List
Keep and publish a top risks list. Make
sure project team members and stakeholders are aware of the top risks, the
causes of the items on the list, the risk control activity being taken, and the
status. As the project manager, you should be concerned about risks that
are on your top risks list for too long.
Click
here to download this Excel Worksheet, or on the spreadsheet sample below.
|
Rank This Week |
Rank Last Week |
Weeks on List |
Risk Description |
Owner |
Org |
Risk Control Activity |
Target Date |
Status |
| 1 |
3 |
2 |
QA Org
overbooked when schedule calls for project testing. |
Bob |
QA |
Coordinate
with other projects to adjust testing schedule |
8/1 |
Open |
| 2 |
2 |
2 |
Code
Management tool upgrade scheduled during build_2 |
Kim |
Systems |
Allow extra
time in build_2 cycle for upgrade problems |
9/15 |
In Work |
| 3 |
4 |
4 |
Lead GUI
developer position not yet filled |
Arthur |
Systems |
Pressure HR
to give this position priority attention |
9/1 |
Open |
| 4 |
10 |
6 |
End users
have not provided meaningful feedback on prototype |
Irene |
Business
Analysts |
Escalate to
next level of management in user community |
7/15 |
Overdue |
| 5 |
5 |
3 |
Development
test systems overdue |
Dmitri |
Systems |
Track
shipping and push assembly through on arrival |
8/1 |
Pending |
| 6 |
6 |
2 |
Five
percent across the board budget cut |
Oscar |
Systems |
Work with
Business Analysts to identify deferrable requirements |
9/1 |
Open |
| 7 |
7 |
2 |
System
Architecture milestones missed |
Deborah |
Systems |
Accelerate
progress through appropriate measures |
9/15 |
Open |
| 8 |
9 |
3 |
Need one
more cube for new tester |
Bob |
QA |
Work with
Facilities to identify possible solutions |
9/1 |
Open |
| 9 |
- |
1 |
Key
developer plans extended vacation in December under "use or lose" policy |
Arthur |
Systems |
Escalate to
Division management for waiver |
10/1 |
Open |
| 10 |
- |
1 |
DBA not
attending project meetings regularly |
Pedro |
Project
Office |
Escalate to
DBA Management |
8/1 |
In Work |